GSK
Client:
GSK GSK
Project:
PHX LTHW and DHWS Upgrade
Location:
Stevenage

ESP undertook the final co ordination/planning and installation of 4No Spirax Sarco plate heat exchanges. This included, the detailed shut downs and planned integration of LTHW and DHWS,  hot tapping the existing LTHW and DHWS works included the full management of the mechanical/electrical/bms/ builderswork and commissioning of the new and dedicated plant to serve a major services building. Pre validation was undertook to read and record base line information for co ordination and ensure post performance results were achieved to design parameters. 

References: References for the above works can be supplied upon request. Project Team: M. Lambourne/K. Roberts/B. Douglas/M. Taker